Building 52 - Exterior Space Enchancement

Project Summary:

This project will enhance outdoor space providing new seating areas and space for students, staff, and faculty to enjoy. Enhancements will include furniture, a living wall, water feature, wind screens, heaters, and additional landscape improvements aimed at creating a tranquil and restorative garden space.

Stage of Development:
Design Development

Location:
Building 52 - Exterior Patio/Breezeway
Project Budget:
$100,000
Timeline:
Planning: September/October 2020
Design: November - December 2020
Bid: February - May 2021
Construction: Upon Project Approval - Summer 2021
Delivery Method:
Contract
Facilities Management & Development Trade Shops
FPCP Project Manager:
Dave Norton
Client:
Facilities Management and Development

Architect:
Design Collaborative