Building 43A Kinesiology - Exterior Envelope Repairs

Project Summary:

This project will repair the exterior building envelope for Kinesiology 43A. Due to envelope failures the building has incurred seasonal water damage resulting in past repairs. These repairs included a roof replacement and resulted in some improvement to conditions. The design team has developed a repair scope and construction will happen Summer 2021.

Stage of Development:
Design

Location:
Building 43A Kinesiology
Project Budget:
$1,100,000
Timeline:
Planning: September 2020 to March 2021
Design: March 2021 to May 2021
Bid: May/June 2021
Construction: June 2021 to September 2021
Delivery Method:
Task Order Construction Agreement
FPCP Project Manager:
Brandon Medeiros
Client:
Facilities Management and Development
Architect:
Harris Architecture
Contractor:
Maino Construction