Building 43A Kinesiology - Exterior Envelope Repairs
|
|
---|---|
Stage of Development:DesignLocation:Building 43A Kinesiology |
Project Budget:$1,100,000 |
Timeline:Planning: September 2020 to March 2021Design: March 2021 to May 2021 Bid: May/June 2021 Construction: June 2021 to September 2021 |
Delivery Method:Task Order Construction Agreement |
FPCP Project Manager:Brandon Medeiros |
Client:Facilities Management and Development |
Architect:Harris Architecture |
Contractor:Maino Construction |