Campus-Wide Cooling Coil Replacement

Project Summary:

Cal Poly is getting all AHU (air handler unit) replace with higher efficiency coils due to microbiologically influenced corrosion. Not to mention the TES tank at the Central Plan is already clean, filter and chemically treated while Facilities Management and Development is working with University Marketing Communication to discuss branding and a repaint of the tank as well.

Stage of Development:
Completed

Location:
Campus-Wide and Central Plant Building 40
Project Budget:
$3 million
Timeline:
Planning: July 2021
Design: August 2021
Construction: August 2021
Occupancy (Temporary Certificate of Occupancy): September 2022
Acceptance (NOC): TBD
Delivery Method:
Job Order Contracts
FPCP Project Manager:
Mitch Dubbers

Client:
Facilities Management and Development
Contractor:
Multiple Contractors