Campus-Wide Cooling Coil Replacement
|
|
---|---|
Stage of Development:CompletedLocation:Campus-Wide and Central Plant Building 40 |
Project Budget:$3 million |
Timeline:Planning: July 2021Design: August 2021 Construction: August 2021 Occupancy (Temporary Certificate of Occupancy): September 2022 Acceptance (NOC): TBD |
Delivery Method:Job Order Contracts |
FPCP Project Manager:Mitch DubbersClient:Facilities Management and Development |
Contractor:Multiple Contractors |