Fremont Slide Restoration
|
|
---|---|
Stage of Development:CompletedLocation:Behind Fremont dormitory area |
Project Budget:$15.8 million |
Timeline:Planning: June 2019 - August 2019Design Development: Winter 2020 Bid/Guaranteed Maximum Price: September 2020 - July 2021 Construction: September 2021 - August 2022 Structural Completion: April 2022 |
Delivery Method:Collaborative Design-Build |
FPCP Project Manager:Eric SoderinClient:California Polytechnic State UniversityUniversity Housing |
Contractor/Engineer:SchnabelYeh Associates Cannon |
Fremont Interior Renovation
|
|
---|---|
Stage of Development:CompletedLocation:Fremont Hall Building 109 |
Project Budget:$5 million |
Timeline:Planning: June 2021Design Development: February 2022 Construction: March 2022 Occupancy (TCO): September 2022 Acceptance (NOC): September 2022 |
Delivery Method:Collaborative Design-Build |
FPCP Project Manager:Paul Fleischer and Sarah MaloneyClient:University Housing |
Contractor:Maino ConstructionArchitect:Harris Architects |