Fresh landscape front of Fremont Hall

Fremont Slide Restoration

Project Summary:

A slow-moving landslide occurred in February 2017 which impacted the Fremont Residence Hall. Residents were relocated and Fremont Hall is currently unoccupied pending resolution of the landslide as a pre-cautionary measure. Facilities Management and Development implemented piping and drainage features to collect and divert surface water, exported some soil, and installed erosion control measures to have the site winterized for Fall/Winter 2018. Nineteen inclinometers were installed to monitor movement. This project will stabilize the slide portion after removing the surface water surcharging.

Stage of Development:
Completed

Location:
Behind Fremont dormitory area
Project Budget:
$15.8 million
Timeline:
Planning: June 2019 - August 2019
Design Development: Winter 2020
Bid/Guaranteed Maximum Price: September 2020 - July 2021
Construction: September 2021 - August 2022
Structural Completion: April 2022
Delivery Method:
Collaborative Design-Build
FPCP Project Manager:
Eric Soderin

Client:
California Polytechnic State University
University Housing
Contractor/Engineer:
Schnabel
Yeh Associates
Cannon

Fremont Interior Renovation

Project Summary:

To prepare dorm for Fall 2022 student occupancy, the dorm will get several areas for improvement such as fire sprinklers and fire alarm systems, roof replacement, carpet replacement(including abatement), and other interior improvements. Additional interior improvements they also focused on: relocating existing laundry rooms to rear of East Lounge and englarging the Kitchen, relocating CSD office to former Mail Room space, adding exterior door to CSD Apartment and relocating East Lounge doors to exterior patio space for improved inside/outside access and repalce dorm room lights with LED fixtures.

Stage of Development:
Completed

Location:
Fremont Hall Building 109
Project Budget:
$5 million
Timeline:
Planning: June 2021
Design Development: February 2022
Construction: March 2022
Occupancy (TCO): September 2022
Acceptance (NOC): September 2022
Delivery Method:
Collaborative Design-Build
FPCP Project Manager:
Paul Fleischer and Sarah Maloney

Client:
University Housing
Contractor:
Maino Construction
Architect:
Harris Architects