Lobby Remodel Fisher Science
Project Summary:This project was funded through Facilities as part of the enhancement budget for Campus Buildings. We chose to update and freshen up the Lobby on the second floor to create a comfortable and inviting study space for students. It is both functional, flexible, and inviting. Due to COVID guidelines, many furniture pieces have been removed and placed in storage until further notice. The space is usable now and still provides new and updated amenities, including lightning and electrical outlets. |
|
---|---|
Stage of Development:100% Design Development Completed |
Project Budget:$105 thousand |
Timeline:Planning: CompleteDesign: DC2 and Dave Norton Bid: Winter - Spring 2020 Construction: June - September 2020 |
Delivery Method:Direct and Trades Shop |
FPCP Project Manager:Dave Norton |
Client:Administration and Finance Departmentand Biological Science Department |