Solar PV and Battery Storage

Project Summary:

The project addresses strategic management of campus utilities by adding about 2.7 megawatts (MW) of solar photovoltaic panels and 1 MW of battery storage to the campus renewable energy portfolio. A power purchase agreement (PPA) is fundamental to the project’s strategic outcome. The initiative will help the campus meet code requirements for future capital projects while supporting the university’s goals for operational efficiency and climate resilience.

Stage of Development:
Planning

Location:
Campuswide
Project Budget:
$12 Million
Timeline:
Planning: Janurary 2024
Preconstruction: May 2024
Construction: December 2024
Occupancy: March 2026
Acceptance: April 2026
Delivery Method:
Power Purchase Agreement
FPCP Project Manager:
Karen Kelly

Client:
Facilities Management & Development, Energy and Sustainability
Contractor:


Architect:
TBD