Comerford Pavilion
|
|
---|---|
Stage of Development:PlanningLocation:Adjacent to the Mustang Tennis Complex. |
Project Budget:$6.5 million |
Timeline:Planning: April 2022Design: August 2022 Construction: April 2023 Occupancy (Temporary Certificate of Occupancy): July 2024 Acceptance (NOC): September 2024 |
Delivery Method:Collaborative Design Build |
FPCP Project Manager:Brandon MedeirosDonor:The Comerford Family |
Client:AthleticsArchitect:TBDContractor:TBD |