Cal Poly Football Center in rendering view

John Madden Football Center


Project Summary:

Cal Poly is in the process of designing a football team facility with the goal of creating a home for the Cal Poly football program. The goal of this building will not only serve daily needs of the team during training time and the regular season, but also serve as a recruitment feature to bring top quality student athletes to campus.

Program proposes a 30,000 sf new two story building with a new team locker room, coach's locker with support spaces; weight rooms, training, rooms and medical support spaces; lounge space including nutrition area; lobby and public/reception/entrance spaces with access to the south end of the stadium, and parking

Stage of Development:
Planning

Location:
Building 61 - Alex G.Spanos Stadium
Project Budget:
$30 million
Timeline:
Planning: April 2021
Design: July 2022
Construction: April 2023
Occupancy (Temporary Certificate of Occupancy): July 2024 - September 2024
Acceptance (NOC): September 2024 - November 2024
Delivery Method:
Collaborative Design Build
FPCP Project Manager:
Brandon Medeiros

Donor:
The Madden Family
Client:
Athletics

Architect:
Populous

Contractor:
PCL Construction