John Madden Football Center
Program proposes a 30,000 sf new two story building with a new team locker room, coach's locker with support spaces; weight rooms, training, rooms and medical support spaces; lounge space including nutrition area; lobby and public/reception/entrance spaces with access to the south end of the stadium, and parking |
|
---|---|
Stage of Development:PlanningLocation:Building 61 - Alex G.Spanos Stadium |
Project Budget:$30 million |
Timeline:Planning: April 2021Design: July 2022 Construction: April 2023 Occupancy (Temporary Certificate of Occupancy): July 2024 - September 2024 Acceptance (NOC): September 2024 - November 2024 |
Delivery Method:Collaborative Design Build |
FPCP Project Manager:Brandon MedeirosDonor:The Madden Family |
Client:AthleticsArchitect:PopulousContractor:PCL Construction |