Cal Poly Football Center in rendering view

John Madden Football Center

Project Summary:

Cal Poly is in the process of designing a football team facility with the goal of creating a home for the Cal Poly football program. The goal of this building will not only serve daily needs of the team during training time and the regular season, but also serve as a recruitment feature to bring top quality student athletes to campus.

The $45M project is Collaborative Design Build delivery method for an approx. 33,000 sf new building with a new team locker room, coach's offices with support spaces, team meeting rooms, weight room, training and medical support spaces; student athlete lounge space including nutrition area; lobby and public/reception/entrance spaces with access to the south end of the stadium, and parking. The project includes South Campus Infrustructure Renewal. The $ 9M enabling work includes repair and replacement of a sanitary sewer, storm drainage, gas, provide 12kv electrical service, ERL fiber communication relocation and broadcast streaming to Spanos Stadium.

Stage of Development:
Construction

Location:
Building 61 - Alex G.Spanos Stadium
Project Budget:
$45 Million
Timeline:
Planning: April 2021
Preconstruction: July 2022
Construction: August 2023
Occupancy: August 2025
Acceptance: September 2025
Delivery Method:
Collaborative Design Build
FPCP Project Manager:
Brandon Medeiros

Client:
Athletics
Architect:
Populous

Contractor:
Hensel Phelps
Leadership in Energy and Environment Design (LEED): Project is pursuing LEED Certification

For more information, click here.

Important Link:

For more information about John Madden Football Center, click here.